CASE DIGEST: BCDA vs. DMCI PROJECT DEVELOPERS, INC. G.R. No. 173137 and G.R. NO. 173170, January 11, 2016

FACTS:
On June 10, 1995, BCDA entered into a Joint Venture Agreement (JVA) with Philippine National Railways (PNR) and other foreign corporations. 

In accord also with the said JVA, BCDA established the Northrail for purposes of constructing, operating and managing the railroad system. The Northrail was registered with the SEC.

The JVA was amended to include D.M. Consunji, Inc. (DMCI) and/or its nominees as an additional investor of Northrail. It shall subscribe to 20% of the increase in Northrail’s authorized stock. The application to increase Northrail’s authorized capital stock was filed with the SEC. The parties also entered into a Memorandum of Agreement infusing initial seed capital of P600 million to Northrail. Out of that amount, P300 million shall be DMCI’s share which shall be converted to equity upon Northrail’s privatization. The P300 million was deposited by DMCI Project Developers, Inc. (DMCI-PDI) into Northrail’s account. DMCI also designated DMCI-PDI as nominee for all the agreements it entered and would enter with them in connection with the railroad project.

Later, Northrail withdraw from the SEC its application for increased authorized capital stock. DMCI-PDI then started demanding from BCDA and Northrail the return of its P300 million deposit for Northrail’s failure to increase its authorized capital stock. However, BCDA and Northrail denied the demand. Thus, DMCI-PDI served a demand for arbitration to BCDA and Northrail, citing the arbitration clause in the June 10, 1995 JVA. BCDA and Northrail claim on the other hand that DMCI-PDI was not a party to the JVA containing the Arbitration Clause.

ISSUE:

Whether the DMCI-PDI may compel BCDA and Northrail to submit to arbitration.

RULING:

Yes. An arbitration clause in a document of contract may extend to succeeding documents of the contract executed for the same purpose. Nominees of a party to and beneficiaries of a contract containing an arbitration clause may become parties to a proceeding initiated based on that arbitration clause.

As it is held, a whole contract may be contained in several documents that are consistent with one another. Considering also that each documents of agreements show that they were executed for the single purpose of implementing the railroad project and that the succeeding documents were executed to amend or supplement the original JVA. Thus, the original JVA and its succeeding documents must be read as a whole document.

In this case, all the documents of agreement shows that they were executed by the same parties. The JVA as amended to include DMCI and/or its nominee, were deemed to have include it as a party to the original JVA executed by BCDA, PNR and the foreign corporations. DMCI and/or its nominee then became bound to the terms of both the JVA and its amendment. Furthermore, the arbitration clause contained in the original JVA is consistent with the terms and conditions of the succeeding documents. Thus, the clause will still be valid and enforceable to the succeeding documents.


Comments

Popular Posts